10/10/2006

RAC Update – 10/10/2006

HVAC 

The masons are working on the southern vertical duct chase.  The steel beams and cribbing that were supporting the northeastern corner of the Mansion’s main block have been removed and Kevin is replacing the barred-window frames.

 

 

About half of the duct work has being installed in the garret.

 

 

The forms for the poured-concrete vault are being set and drainage is being installed. 

M-111 (Back Chamber) 

Mac Ward, Steve Chronister and Les Lamois have finished laying the floors in this space.

 

M-110 (Period I Stairs)

Mac and Steve are preparing to frame the period I stairs

Garret 

Austin has started to replace the principle rafter that continues into the portico from the main block’s roof. 

Colonnade  

New heart pine decking is being laid on first floor deck.

Wing Roofs 

The decking panels continue to be installed and preparations are being made for installing the Chinese rails.

 

 

 

Red Room Re-Installation 

 

The Red Room Chimney piece has arrived at the visitor center un-harmed and it should be installed this week.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: