RAC Update – 10/23/2006

HVAC 

The masons have finished lining the vertical duct cases and are finishing underpinning the foundation in the cellar.

The mud slab for the HVAC vault was poured last Thursday and the vault is being prepared for the wall and floor forms.

The HVAC ducts continue to be installed in the garret and the electricians are running conduit.

M-109 

Keith has installed approximately ¼ of the flooring on the eastern end of this space.  The new flooring is face nailed heart pine similar to what was installed in M-111 and M-112.

M-110 (Period I Stairs)

Mac has cut six stringers for the new stair and the first stringer has been installed against the south wall of M-110. 

M-206

Wayne M. has finished re-securing the lath on the ceiling of this room in preparation for re-plastering.

M-209 

Wayne has started to install re-used riven lath on the ceiling in this room (almost all of the original lath had been replaced with wire lath).  The riven lath is coming from off-site donations and is being secured with ribbed, stainless-steel nails. 

Garret 

Austin has started to replace two common rafters in the section of the roof that was trapped by the c. 1797 portico addition.  Only the portion of the rafters that ran from the ridge down to the purlin will be replaced.

Colonnade  

New heart pine decking continues to be laid on first floor deck by Bill and Nick.

Wing Roofs 

The decking panels continue to be installed and preparations are being made for installing the Chinese rails.

  

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: