RAC Update – 2/5/2007

HVAC/MEP 

Work on the electrical, fire suppression, VESDA, and temperature/humidity monitoring systems continues. 

The subterranean fiberglass ductwork continues to be installed throughout the cellar.

The forms for the bunker entrance walls are being constructed.

M-101 (North Wing Closet and Stair enclosure)

 Les Lamois is framing the stair enclosure for the north cellar stairs  

M-106 (North Passage)

Mac Ward is leveling the framing for the small, Madison-era second floor landing that survives in situ.  We plan to re-use this framing, although dutchmen, additional bracing and epoxy treatments will most likely be needed before the new carriages are attached. 

Re-used riven lath is also being installed in the western portion of this space.  

M-110 (Period I stair enclosure)

Keith Forrey has installed the headers for the doorways into this space.  

M-111 (Back Chamber)

The top portion of the re-constructed chimney breast has been completed.  It had been left unfinished in order to install duct work. 

M-112 (Old Dining Room)

The closet under the stair is being lathed with re-used riven lath  

Chinese Railings

The top rails have being installed on the north and south wings. 

  

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: