RAC Update – 3/12/2007

HVAC/MEP 

Work on the electrical, fire suppression, VESDA, and temperature/humidity monitoring systems continues. 

Installation of the subterranean fiberglass ductwork in the cellar has almost been completed.

The membrane covering for the roof and sides of the bunker is being installed and the concrete steps leading into the bunker have been poured.

M-001 (Dolley’s Kitchen)

The masons are installing re-used heart-pine lath as needed on the ceiling of this space (mostly on the southern portion of the ceiling) 

M-104 (Mr. Madison’s Room) 

The masons are installing re-used riven lath in this space and preparing the existing lath to receive the new plaster.

M-105 (New Dining Room)

Keith Forrey has finished repairing the flooring in front of this fireplace.

M-107 (Entry) 

The Madison era trim for the north and south arched doorways leading from this space are being prepared for re-installation.

M-201 (Large Bedroom) 

The masons have finished working on this fireplace.

M-209/M-211 

Mac Ward is installing the re-constructed door casing between these two rooms.

Cellar

Bill Bichell continues to repair window stools and window boxes for the wing windows.

Chinese Railings

Ed Gomez and Austin Atrim are installing the fretwork for the Chinese rails on the North wing deck.  They are approximately halfway through.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: