RAC Update – 4/3/2007

Trim

Blaise Gaston continues to mill the elements for the trim that will need to be reconstructed. 

HVAC/MEP 

Work on the electrical, fire suppression, VESDA, and temperature/humidity monitoring systems continues and portions of the duct and MEP channels in the cellar continue to be infilled.

The retaining wall around the vault is being removed and they are slowly infilling the builder’s trench.  Also, the installation of air handlers and other equipment in the vault continues.

M-002 (North Cellar Passage)

The masons have started to install re-used lath as needed on the ceiling of this space.  

M-109 (South Passage) 

The two, bronze floor registers have been installed in this room.

M-208 (Chamber) 

The reconstructed doorway from this room into the Upper South Passage has been installed.  Nick has also replaced the deteriorated baseboard nailers along the eastern wall.

 M-211 (Southeastern Chamber) 

Mac Ward and Austin Atrim have almost finished trimming this space.

   

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: