RAC Update – 5/29/2007


MEP work continues in the bunker.  The floors in the two wing kitchens are also being prepared for the radiant heating system. 


The mason’s continue to re-secure the existing lath and install re-used lath where needed.

M-201 (Large Bedroom) 

Mac Ward is trimming the door to the north wing deck. 

M-207 (Southwest Chamber) 

Ed Gomez continues to install chair board. 

M-209 (Upper South Passage) 

Austin Antrim has installed the chair board base and is currently installing the torus molded surbase. 

Interior Trim 

Keith Forry and Bill Bichell are preparing the entry’s arched door surrounds and the drawing room’s paneled jambs for re-installation.


Wayne Mays has started to apply the final coats of rendering to the pilasters. 


Wit Jacobs continues to clean the repointed or replaced sections of exterior brickwork.


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: