Montpelier Restoration Update – 8/15/2007

HVAC/MEP

Geothermal pipes

The pipes that will run water from the geothermal wells to the heat exchangers in the mechanical bunker are being installed.

reestablished grade

 

The Madison grade is also being re-established on the east elevation in preparation for moving the handicap access ramp to the rear colonnade. Having the ramp on east elevation will allow the handicap ramp on the western façade to be removed and everyone is looking forward to seeing the mansion’s main elevation cleared of modern intrusions.

generator

The generator for the Mansion’s electrical, HVAC and security systems has also been installed.

Plastering

floating 212

A Mason Using a Darby to Level the Brown Coat in M-212 (Southwest Chamber)

Scratch coat and brown coat plaster are being applied below the chair rails in M-211 (southeastern bedroom) and M-212 (southwestern bedroom). Brown coat is also being applied to the walls of M-201 (large bedroom) and a finish coat has been troweled onto the walls in M-208 (passage chamber).

M-009 (Nelly’s Kitchen)

prep nelly’s kitchen paving

The masons are preparing to lay the brick paving in this kitchen. A running bond pattern will be used (instead of the herringbone found in Dolley’s kitchen). Evidence for this bond pattern was found archaeologically and it indicates that this kitchen, which was used by Madison’s widowed mother, had a slightly lower status then Dolley’s kitchen.

M-100 (North Wing Chamber)

reused archtrave

Bill Bichell Holding the Re-used Section of Architrave

Bill Bichell has started to prepare and install the architraves for the windows. Amazingly, one of the original ca. 1812 architraves for this room was recently discovered among the Madison trim work that the duPont’s reused during their 1901 renovations.

keith cutting slot for new flooringrepairing floor in splayed jambs 100

Keith Forry is also restoring the flooring found in the windows’ and doorway’s splayed jambs. New heart pine patches, which will match the original Madison flooring, are being used. The original Madison flooring was removed in 1901 when the duPonts infilled the doorway with brick.

M-200 (Small Bedroom)

installing chimney piece in 200

Ed Gomez is finishing the installation of the surbase and baseboard. The Whitehaven sandstone hearth for this room is still being quarried in England and so the chimney piece has been temporarily installed

M-205 (Upper North Passage)

mac sawing newel

Mac Cutting a Tenon for a Newel

Mac Ward is installing the last two newel posts, including the first floor newel, and the blocking for the stair’s paneling.

Colonnade

Austin Antrim continues to install the cornice.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: